Lumber Liquidators logo

Wood Grill Vent Installation




Unfinished / Prefinished Wood Vent Installation

Flush with Frame Vent

Drop In Vent



Lumber Liquidators

Wood vent sizing

Order Size

Overall Size Flush w/ Frame

Overall Size Drop In

2 x 10

4-15/16 x 12-13/16

3-3/4 x 11-1/4

2 x 12

4-15/16 x 14-13/16

3-3/4 x 13-1/4

2 x 14

4-15/16 x 16-13/16

3-3/4 x 15-1/4

4 x 10

6-3/4 x 12-13/16

5-3/16 x 11-1/4

4 x 12

6-3/4 x 14-13/16

5-3/16 x 13-1/4

4 x 14

6-3/4 x 16-13/16

5-3/16 x 15-1/4

6 x 10

8-3/4 x 12-13/16

7-3/16 x 11-1/4

6 x 12

8-3/4 x 14-13/16

7-3/16 x 13-1/4

6 x 14

8-3/4 x 16-13/16

7-3/16 x 15-1/4

Unfinished Wood Vent Installation Instructions

Flush with Frame Model - (Flush vents should be on site during installation of wood flooring)

1)    Center frame over duct opening.

2)    Glue and/or pre-drill and hand nail frame to sub floor to prevent splits.

3)    Install flooring up to frame.

4)    Fit vent into frame and sand the vent along with floor to level it with the frame and floor.

When sanding floor, DO NOT RUN WHEEL OF SANDER OVER THE VENT FACE. THIS MAY BREAK THE LOUVERS OF THE VENT.

5)    Remove vent from frame and finish the vent and floor separately.

6)    Finish all exposed surfaces (face, back, edges) including between louvers before fitting vent into frame. 

Drop In Model -

1)    Finish all exposed surfaces (face, back, edges) including between louvers.

2)    Remove old register and replace with the finished drop in wood vent.

Prefinished Wood Vent Installation Instructions

Flush with Frame Model - (Flush vents should be on site during installation of wood flooring)

1)    Center frame over duct opening.

2)    Glue and/or pre-drill and hand nail frame to sub floor to prevent splits.

3)    Install flooring up to frame.

4)    Fit vent into frame.

Drop In Model -

1) Remove old register and replace with the finished drop in wood vent.